|
LandMark Design Group was selected by the Virginia Department
of Transportation, in the spring of 2000, to provide the design
for the Princess Anne Road/Ferrell Parkway Improvement Project.
Ferrell Parkway was renamed Nimmo Parkway by the City of Virginia
Beach after we started work on the project. We are providing
the following services: roadway construction and landscape
plans, wetlands delineation, acquiring a Corps of Engineers
jurisdictional wetland confirmation, acquiring all federal,
state and local wetland permits, and locating and designing
wetland mitigation sites to compensate for unavoidable wetland
impacts.
The project is located in the southern portion of Virginia
Beach near the municipal center and the Princess Anne Commons
area. The project begins just south of Dam Neck Road, near
the Virginia Beach Amphitheater, and ends at the Nimmo Parkway
stub west of the intersection with General Booth Boulevard
(near the Princess Anne Recreation Center). In 1999, we completed
the Princess Anne Road/Ferrell Parkway Location Corridor Study
for VDOT. This study set the corridor for the horizontal alignment
of the roadway. The horizontal alignment for Princess Anne
Road was also driven by the Princess Anne Corridor Study completed
by the City of Virginia Beach and adopted by City Council.
We designed the Ferrell Parkway portion of this project for
the City of Virginia Beach approximately 10 years ago but
it was shelved because of funding problems.
Why improve Princess Anne Road and construct Nimmo Parkway?
A transportation study of the Princess Anne Road Corridor
determined that current traffic volumes on Princess Anne Road
far exceed the capacity of the roadway. Traffic congestion
and increasing delays at the intersections reduces travel
speeds. The proposed improvements will increase traffic capacity,
decrease congestion and delay, provide for future traffic
needs, and correct geometric deficiencies, including narrow
pavement and shoulders , and deep roadside ditches. The Nimmo
Parkway section of the project will route traffic around the
historic Princess Anne section of the City.
The Princess Anne Road segment of the project begins just
south of Dam Neck Road to Nimmo Parkway and includes the segment
of Ferrell Parkway (Nimmo Parkway) from Princess Anne Road
to Holland Road. The total length of this segment is 2.4 miles.
The project will widen Princess Anne Road from a narrow two-lane
roadway (Figure 1) to
an ultimate eight-lane roadway with paved shoulders, a landscaped
median, and multi-purpose paths on each side. We will design
four lanes of the roadway initially. The median will be wide
enough to allow for construction of the additional four lanes
in the future. The 250 foot right-of-way section (Figure
2) allows for increased areas of landscaping for the gateway
to Princess Anne Commons and the City of Virginia Beach Municipal
Center. A 30 foot landscaped area including a berm, street
lighting fixtures, and shallow drainage swales will separate
the (Figure 1) existing Princess Anne Road roadway from the
sidewalk.
This section of the project also includes the construction
of Nimmo Parkway from Princess Anne Road to Holland Road on
new alignment. Nimmo Parkway will be a six-lane roadway ultimately
(Figure 2). Four lanes
will be designed and constructed initially. The roadway will
have space in the landscaped median to construct the two additional
lanes in the future. The 230 foot right-of-way allows for
a 50-foot landscape darea between the sidewalk and the proposed
right-of-way limits. The alignment of Nimmo Parkway was set
by the location of Kellam High School to the south and the
(Figure 3) historic Burroughs House property to the north.
(Figure 3) The design
of the intersection with Holland Road is also included. To
accomplish this, we are coordinating with URS who is currently
designing the Holland Road widening to four lanes in the vicinity.
The remainder of the project is the construction of Nimmo
Parkway, on new alignment, from Holland Road to the existing
stub near General Booth Boulevard. The total length of this
segment is approximately 1.8 miles. The right-of-way varies
from 116 to 151 feet due to its proximity to existing neighborhoods
and wetlands. The existing neighborhoods are near Holland
Road and the existing Nimmo Parkway stub. The wetland impacts
of most concern are those adjacent to West Neck Creek (Figure
4). All of the segments include four lanes with space
in the median to construct two additional lanes in the future,
curb and gutter instead of ditches for drainage, a multipurpose
walk to the north, and landscaping and lighting fixtures to
the outside. The subdivisions, wetland impacts, and an existing
30-inch HRSD force main drove the alignment. Currently, we
are working (Figure 4)
with VDOT, the City of Virginia Beach, and the Corps of Engineers
to determine the bridge location and length. The West Neck
Creek crossing will be between 1,150 feet (the minimum as
determined by the hydraulics study) and 1,500 feet (increasing
the width to the west to save some higher quality wetlands).
The environmental work was initiated in the summer of 2000.
Presently the wetland delineation, Corps confirmation and
survey of all of the wetlands impacts have been completed
for the 4.2 mile roadway. The wetland delineation included
areas of farm fields, fallow fields, mesic forest, freshwater
marsh, and the associated floodplain along West Neck Creek.
The Princess Anne Road segment of the project will impact
4.80 acres of wetland, and the Nimmo Parkway portion of the
project will impact 10.89 acres of wetlands, for a total mitigation
wetland compensation cost of nearly $2 million dollars.
|
|
|
|
Figure 1:
Existing Princess Anne Road
|
| |
|
|
|
Figure 2
(Click
image to enlarge)
|
| |
|
|
Figure 3: Nimmo Parkway
Right-of-way
Reservation
|
| |
|
|
Figure 4: West Neck Creek
|
| |
|
|
Figure 5: IACM Presentation
|
| |
|
|
Figure 6: Right-of-way
Relocation Assistance
|
| |
|
|
Figure 7: Gary Webb answering
questions from councilperson Barbara Henley
|
|
|
The most difficult hurdle in this project is obtaining
all of the wetland permits, which requires us to find
suitable wetland compensation sites. This is difficult
because we need in-kind replacement, which means that
we have to find replacement wetlands for the swamp tupelo,
green ash, and red maple forest, which is a freshwater
tidal habitat. Habitats such as these are difficult
to mimic because they are difficult to establish. We
have been closely working with the Corps of Engineers
to reduce impacts on the Nimmo Parkway portion of the
project through the West Neck Creek floodplain, by increasing
the length of the bridge through this area and decreasing
the footprint of the roadway by landscaping on the side
slopes. We are presently completing a mitigation site
search from the Dam Neck Road and Princess Anne Road
intersection to the southeastern edge of the Virginia/North
Carolina border. Between 51 and 204 acres of existing
wetlands in the West Neck Creek and or North Landing
River watershed, along with the creation or restoration
of 16 acres of wetlands could be required by the state
and federal agencies.
In March 2001, the project was presented at the Interagency
Coordination Meeting (IACM) in Richmond (Figure
5). Early coordination effort with the agencies
is key to addressing all potential issues of concern
prior to the permit application, strengthening our relationship
with the agencies, and increasing the likelihood of
a smooth permit review in 2002.
On August 1, 2001, LandMark Design Group conducted
a Citizen Information Meeting, in conjunction with the
Virginia Department of Transportation and the City of
Virginia Beach, for the Princess Anne Road segment of
the project. (Figures
6 and 7) The
meeting was held at Landstown Elementary School from
4-7 p.m. Most of the attendees were those who will be
displaced as a result of the project. The next project
milestone is the Field Inspection planned for March
2002. Citizens will have another opportunity to view
the design and talk with designers at the Design Public
Hearing scheduled for mid 2002.
The design and posted speed limit will be 45 mph for
the project. Current estimated costs are $7.4 million
for the right-of-way and $11.1 million for the construction
of Princess Anne Road and $2.1 million for the right-of-way
and $22.4 million for the construction of Nimmo Parkway.
Aquarius Engineering is a sub consultant to us for the
all hydraulic analysis, hydraulic design, and preparation
of the erosion and sediment control plan. Hardesty and
Hanover is completing a bridge concept study and will
design and prepare construction plans for the bridge.
|
|